Photographic history of 2008/9 clubhouse development
Before the change 21st Nov 2008
12th Jan footings are in
12th Jan footings are in and mower shed is no longer
12th Jan container is just visible from the clubhouse :-)
12th Jan footings are in and so is the shower room floor
19th Jan signs of life! Meet Martin Chomistek
19th of Jan more signs of life but at a lower stage in development. Meet Jon Golby
19th Jan block work to get to DPC level
19th Jan block work to get to DPC level on old tool shed
19th Jan interior looking towards the bar
19th Jan interior looking though to the kitchen from the home dressing room.
19th Jan interior looking towards the showers / toilets from the away dressing room
19th Jan interior looking towards the home dressing room from the showers
19th Jan interior looking towards from the bar to the kitchen and dressing rooms
9th Feb work moving on inside because of snow. The old bar store
9th Feb work moving on inside because of snow. The support beam and internal walls to support the roof are installed. Note Martin's hankie work
9th Feb work moving on inside because of snow. Front wall re-inforcement
9th Feb work moving on inside because of snow. The sudden thaw provides a water feature
9th Feb work moving on inside because of snow.
9th Feb work moving on inside because of snow. Some brave men atempt to do stuff with a digger
9th Feb work moving on inside because of snow. Attempts made to remove surface water
9th Feb work moving on inside because of snow. Scaffold up to assist with block work to roof level
9th Feb work moving on inside because of snow. Rear view from road showing scaffold and toilet block
9th Feb work moving on inside because of snow. Rear view of block work progress
9th Feb work moving on inside because of snow. More rear block work
9th Feb work moving on inside because of snow. The old tool shed soon to be kitchen
9th Feb work moving on inside because of snow. View from the boundary
9th Feb work moving on inside because of snow. The front view of the new kitchen block
9th Feb work moving on inside because of snow. Front view from the new kitchen to the road
9th Feb work moving on inside because of snow. View from the gate
22nd Feb blockwork almost complete
22nd Feb missing the flat roof over the the front of the club house
22nd Feb view from the scaffold from the new kitchen towards the road
22nd Feb view from the scaffold from the back through the bar store into the kitchen
22nd Feb view from the scaffold from the rear towards the road and container
22nd Feb view from the scaffold towards the new kitchen from the back
22nd Feb view from the scaffold
22nd Feb view from the scaffold from the new dressing room towards the bar and kitchen
22nd Feb tree work
22nd Feb view from the old dressing room towards the scoreboard without the roof
22nd Feb view from the gate
28th Feb 2009 - Last day of winter and the roof is being built
28th Feb 2009 - Last day of winter
28th Feb 2009 - Last day of winter. View from the scaffold
28th Feb 2009 - Last day of winter. View under the new eaves
28th Feb 2009 - Last day of winter. The end wall
28th Feb 2009 - Last day of winter. View down the roof space
2nd March. Spring and the temporary green tarpaulin is installed as the last if the old roof is removed
2nd March. Spring and the Lee's Berlin Wall is coming down
2nd March. Spring and the wall is partially remove revealing the massive interior of the new club house
2nd March. Spring and a view form the outfield
2nd March. Spring and a view through the roof space
2nd March. Spring and bits of stick, string and no more nails hold the structure together.
2nd March. Spring and a view to the floor from the roof. Not a great photo
2nd March. Spring and a view of the see through roof designed by JG
2nd March. Spring and some more hankie wrok from Martin
2nd March. Spring and JG is visibily growing in stature as he inspects more work done by someone else
2nd March. Spring and a view of the hanging gardens. Rustic cement mixer picture right
2nd March. Spring and more of the Berlin wall equivalent
2nd March. Spring and a new hole is formed where there was a perfectly serviceable door and wall.
2nd March. Spring and a new freind joins the contsruction duo. Meet Roy Crockford
6th March Topping out, the new inside
6th March Topping out, view from the new home dressing room through old kitchen to club house
6th March Topping out, new away dressing room
6th March Topping out, new home dressing room
6th March Topping out, the ladies and disable loo
6th March Topping out, the old rood supporting wall is removed
6th March Topping out
9th March refixing the temporary roof after storms
16th March a beautiful spring day and the mens toilet wall is bult
16th March a beautiful spring day and more block work goes up
16th March a beautiful spring day and Mick a beautiful brickie enjoys his cuppa
16th March a beautiful spring day, Peter destroys a perfectly good roof
16th March a beautiful spring day
16th March a beautiful spring day, why does this take so long to build?
16th March a beautiful spring day and we are making progress
22nd March flat roof on showers and disabled toilets
22nd March the indoor nets proposed within the roof space!
22nd March view from the scaffold
22nd March the clock housing from the scaffold
22nd March the clock housing from the scaffold looking towards the road
22nd March the first slates go down
22nd March the clock housing from the ground
22nd March the view from the square showing the clock housing
29th March after the clocks went forward. The club house felted and battened.
6th April Cricket Force Weekend and the 2nd fixings are done, clubhouse from the inside
6th April Cricket Force Weekend and the 2nd fixings are done, clubhouse from the inside looking toward kitchen
6th April Cricket Force Weekend and the 2nd fixings are done, clubhouse from inside the new kitchen
6th April Cricket Force Weekend and the 2nd fixings are done, clubhouse with lighting cables installed
6th April Cricket Force Weekend and the 2nd fixings are done, away dressing room
6th April Cricket Force Weekend and the 2nd fixings are done, home dressing room
6th April Cricket Force Weekend and the 2nd fixings are done, clubhouse facia boards
6th April Cricket Force Weekend and the 2nd fixings are done, clubhouse from the left front
6th April Cricket Force Weekend and the 2nd fixings are done, clubhouse from the front
6th April Cricket Force Weekend and the 2nd fixings are done, clubhouse from the right
17th April and the day the scaffold came down
17th April and the day the scaffold came down and the name is back above the door
17th April and the day the scaffold came down with the name above the door
17th April and the day the scaffold came down and the first pint was imagined
17th April and the day the scaffold came down. The view down the veranda
17th April and the day the scaffold came down. The view to the home dressing room door
17th April and the day the scaffold came down. The shower block
17th April and the day the scaffold came down, the naked rear
17th April and the day the scaffold came down and the new toilet arrived
17th April and the day the scaffold came down, view from kithen to bar.
17th April and the day the scaffold came down, Martin pacing his run out
17th April and the day the scaffold came down, Mick the Bricks wonderful bar work
17th April and the day the scaffold came down. Meet Nigel the sparks.
17th April and the day the scaffold came down and the bar top was moved
17th April and the day the scaffold came down. The bar top in its resting phase outside
3rd May rapid progress and we are in full flow. The bar with lights and flowers.
3rd May rapid progress and we are in full flow, the bar with lights
3rd May rapid progress and we are in full flow, the bar again
3rd May rapid progress and we are in full flow
3rd May rapid progress and we are in full flow, the kitchen with work surfaces
3rd May rapid progress and we are in full flow, the kitchen sink
3rd May rapid progress and we are in full flow, so what makes you think that the bar is important?
3rd May rapid progress and we are in full flow, clubhouse view
3rd May rapid progress and we are in full flow, toilet block functional but instructions are still required for it's use
3rd May rapid progress and we are in full flow, the away dressing room
3rd May rapid progress and we are in full flow, the home dressing room
3rd May rapid progress and we are in full flow, access to the roof space from home dressing room. Pete Hall's winter residence?
3rd May rapid progress and we are in full flow, the doors (temp) are installed
3rd May rapid progress and we are in full flow. The best club house in Bucks
3rd May rapid progress and we are in full flow. The outside viewing deck awaits expansion
3rd May rapid progress and we are in full flow, the rear view with drains installed
3rd May rapid progress and we are in full flow, the main drain area
1st June the sun is shining and the clock goes up
4th June with clock erected
First game of the season 2010 v Amersham Hill
Club house topping out with proud donor John Andrews.Thank you John!
Club house topping out JG gets his finger stuck and is there for the duration
Club house topping out. Job done!